News

Placing concrete for the foundation slab of engine room No. 5 in Power Plant Opole

From 25th to 28th February was placed concrete for the foundation slab of engine room No. 5. The slabs dimensions are 51 x 108 m and a variable height from 1.7m to 3.5m. Placing the concrete was done using 5 pumps ( at the peak even 6), 24 hours a day and lasted 72 hours. The total amount of used concrete was about 11 200 m3.